NPS III for Urea Manufacturing Units & Amendments (10.07.2009)

Stage-llI of NPS Amendments:

1. The capacity utilization of post 1992 Naphtha based Group
average will be considered as 95% instead of 98% for
Calculating the base concession rates of urea units, provided
no cost towards conversion is recognized under NPS-lll.
2. The reduction in fixed cost of each urea unit strictly due to
Group Average principle under NPS-lll will be restricted to
10% of the Normated Fixed Cost computed under the base
concession rates.
3. The detailed parameters for Buffer-Stocking Scheme of urea
will be as per the provisions. For more information, please go to attached notification.